The Society will consider lending to customers requiring self-build mortgage facilities, subject to the following criteria:
The following stage releases apply, however a flexible approach can be exercised for each case:
Percentage of Advance to be released
|
Stage
|
Phase
|
Max % of current value for funds release
|
1
|
Land purchase
|
85%
|
2
|
Initial project costs and laying foundations
|
85%
|
3
|
Construction to wall plate level
|
85%
|
4
|
Building made wind and watertight
|
85%
|
5
|
First fix and plastering
|
85%
|
6
|
Second fix through to certified completion including landscaping
|
85%
|
Note with regard to stage 1, where the applicant already owns the land, 50% of the value of the land, up to a maximum of 85% of the total loan amount, may be released up front (see examples below).
Example 1: Total loan amount required is £100,000 and land value is £50,000. Therefore the full 50% of the land value can be released up front (£25,000) as this only represents 25% of the total loan amount.
Example 2: Total loan amount required is £25,000 and land value is £50,000. Therefore, as 85% of the total loan amount only equates to £21,250, this would be the maximum that could be released up front (even though 50% of the land value would be £25,000).
- Up to stage 4, the maximum loan amount released will be 85% of the current value at each stage. At stages 5 and 6, we will release the remaining funds up to a maximum of 85% of the current value at each stage. The amount of funds released at each stage will be subject to valuer’s comments
- The Society reserves the right to carry out interim valuations during any stage of the build. A re-inspection will be required at each stage prior to funds being released to the customer. The fee for this service will be payable by the customer and can be found in the List of Charges document
- Knock-down rebuild remortgage – Customers must be able to reduce the mortgage based on the low value point i.e. the valuation on special assumption of a cleared site with consent to build (first stage)
-
Expat applications will be considered and normal expat criteria will apply. In addition to this we will require:
- Gifted deposits will be accepted. Funds from family members to assist with initial cash flow costs, that are agreed to be re-paid, will also be accepted however this will need to be included in the schedule of costs. It would also need to be incorporated into the last release of funds
- Ten years structural warranty is required. List of main providers are held on the UK Finance Handbook. Other providers may be considered subject to checks of the UK Finance handbook
- Site insurance and a copy of the insurance schedule will be required with a minimum of the following included:
-
£5 million public liability
-
£10 million employers’ liability
-
Contract works (for the re-instatement value)
-
Dudley Building Society to be noted as mortgagee
-
Site insurance will be accepted from a set list of providers. Other providers may be considered subject to checks of the UK Finance handbook
-
Before building commences the valuer must have sight of the detailed planning and building regulations approvals. A Builders Notice will not be acceptable
-
The building work must be supervised by a suitably qualified Architect. All Architects supervising the build must have Professional Indemnity cover of no less than £1m and one of the qualifications below:
-
ARB UK Architects Registration Board UK (previously known as ARC)
-
*RIBA / ARIBA / FRIBA Chartered Member/Associate/Fellow of the Royal Institute of British Architects
-
MCIAT Corporate Member of the Chartered Institute of Architectural Technicians
-
MASI/FASI Corporate Member/Fellow Member of the Architects and Surveyors Institute (excludes AMSI)
-
C. Build E MCABE/ C. Build E FCABE Chartered Member/Chartered Fellow of the Chartered Association of Building Engineers (excludes A B Eng)
-
MICE/ FICE Member/Fellow of the Chartered Institute of Civil Engineers (Excludes AMICE)
-
FCIOB/MCIOB Fellow or Member of the Chartered Institute of Building
-
MRICS / FRICS Member or Fellow of the Royal Institution of Chartered Surveyors (RICS)
-
MI Struct Eng/ FI Struct Eng Chartered Member or Fellow of Institute of Structural Engineers
*only acceptable if also registered with the Architect’s Registration Board (ARB).
Golden Brick
DBS will lend on 'Golden Brick' development, i.e. where the applicant is buying a serviced plot to DPC level. This would be subject to valuer comments on future saleability of the property and care should be taken to understand the surrounding properties and potential impacts.
Advanced Stage Releases:
Typically, stage releases will be released in arrears of work being complete. Stage releases in advance of work being complete can be considered subject to the following criteria being met:
-
The Society has a product available for advanced stage releases
-
The Society is able to take a charge on a second property, the property must have sufficient equity to cover 50% of the required loan amount (including the contingency fund)
-
A valuer shall be instructed prior to each stage being released to ensure progress is being made and the end value is still on target
-
Final maximum LTV of 85%
-
The following stage releases apply
Maximum Percentage of Advance to be released
|
Stage
|
Phase
|
|
1
|
Land purchase
|
80% of Land Value
|
2
|
Initial project costs and laying foundations
|
20% of build costs capped at £150,000
|
3
|
Construction to wall plate level
|
20% of build costs
capped at £150,000
|
4
|
Building made wind and watertight
|
20% of build costs capped at £150,000
|
5
|
First fix and plastering
|
20% of build costs capped at £150,000
|
6
|
Second fix through to certified completion including landscaping
|
20% of build costs capped at £150,000
|
All advances stage payment applications will be subject to enhanced mandating.
Eco Self-Build
The Society will allow Eco Self-Build properties. An Eco Self-Build can be defined as a property which is anticipated to have an EPC rating of A or B and at least one eco feature. Eco features could include:
-
Higher than normal levels of thermal insulation
-
Better than normal airtightness
-
Good levels of daylight
-
Passive solar orientation — glazing oriented south for light and heat
-
Thermal mass to absorb that solar heat
-
Minimum north-facing glazing — to reduce heat loss
-
Mechanical ventilation with heat recovery (MVHR) system
-
Heating from renewable resources (such as solar, heat pump or biomass)
-
Photovoltaic panels, small wind turbine or electricity from a ‘green’ supplier
-
Natural materials — avoidance of PVCu and other plastics
-
Rainwater harvesting
-
Greywater collection
-
Composting toilet
-
Glass that has two or three layers with a vacuum in between to prevent heat loss; (double or triple-glazed windows)
-
Solar panels or wind turbines
-
Geothermal heating and growing plants on the roof to regulate temperature, quieten the house, and to produce oxygen
Eco-Self Builds will be subject to valuer comments.